Hampshire Rewires supplied and installed a new Hypervolt Home 3 Pro EV charger at a residential property in Winchester.
The installation required a completely new dedicated electrical supply from the property's main electrical intake, together with approximately 35 metres of EV charging cable.
New electrical supply and protection
We installed a separate consumer unit inside the existing meter cabinet, taking the new supply from the main electrical intake.
The consumer unit incorporated:
- Double-pole RCBO protection.
- Surge protection (SPD).
This provided a dedicated protected supply for the new EV charger.
EV charger cable installation
We installed approximately 35 metres of 6mm² EV Ultra cable, incorporating additional data cabling.
The cable was clipped directly to the external brickwork along its route from the meter cabinet to the charger location.
The Hypervolt Home 3 Pro was installed externally, with its 7.5-metre charging cable and connector holder.
Hardwired internet connection
Due to the distance between the house and the charger, the property's Wi-Fi signal could not reliably reach the installation location.
To overcome this, we installed a hardwired internet connection.
An internet cable was brought from the house to a junction box inside the meter cabinet. The data conductors incorporated within the EV Ultra cable were then used to carry the connection to the charger.
This avoided relying on a weak wireless signal.
Connectivity problems and fault finding
Following the original installation, the charger experienced intermittent internet connectivity problems.
The connection repeatedly dropped out, requiring us to return to the property on separate occasions to investigate.
We checked several connections and worked through the possible causes to identify the source of the problem.
After further investigation, the fault was traced to the charger itself rather than the cable installation.
Hypervolt arranged a replacement charger without any difficulties.
Once the replacement unit was installed, the internet connectivity problems were resolved, and no further issues were experienced.
Installation timescale
The original installation was completed in one full working day, including:
- Installing the dedicated consumer unit.
- Running approximately 35 metres of EV Ultra cable.
- Installing the hardwired data connection.
- Mounting and connecting the Hypervolt charger
- Testing and commissioning the installation.
Additional visits were carried out afterwards to investigate the intermittent internet connection.
Testing and certification
Following installation, the electrical work was inspected and tested.
An Electrical Installation Certificate (EIC) was issued, and Building Regulations notification was completed through NICEIC.