We recently carried out a consumer unit replacement in Stockbridge, Hampshire. The property had an ageing Wylex fuse board, believed to have been installed when the house was originally built around 1980.
The existing consumer unit contained a mixture of older plug-in fuse carriers and miniature circuit breakers (MCBs).
There was also a separate Contactum RCD enclosure serving the shower circuit, together with additional electrical control equipment associated with the property's heating system.
The customer wanted the ageing installation replaced with a modern consumer unit incorporating individual RCBO protection and surge protection.
Removal of existing equipment
We removed the old Wylex consumer unit, the separate shower RCD enclosure and an existing contactor.
Two existing heating timers were retained. These controlled the immersion heater and three electric heaters within the property.
Both timers were reconnected to the new installation to maintain the existing heating controls.
New Navitas consumer unit
We supplied and installed a new Navitas consumer unit incorporating:
- Individual RCBO protection for the circuits.
- Surge protection (SPD).
- New 25mm² meter tails.
- New 16mm² main earthing conductor.
The replacement provided a modern arrangement with individual residual current and overcurrent protection for the connected circuits.
Installation challenges
The main challenge was the condition and arrangement of the existing cabling.
All the original circuit cables were too short to connect directly into the new consumer unit.
In addition, the cables entered the installation area from several different directions, with existing conduit and cable routes that needed to be accommodated.
We installed new trunking to provide a suitable route for the existing cables and their extensions.
Each circuit cable needed to be extended and carefully routed into the new consumer unit.
This made the installation considerably more time-consuming than a straightforward fuse board replacement.
The completed arrangement also allowed us to retain and reconnect the two existing heating timers beneath the new consumer unit.
Working in an occupied property
The customers were living in the property throughout the installation.
The electricity supply was isolated during the working day while the old equipment was removed and the replacement installed.
Despite the additional work involved in extending the existing cables, the new consumer unit was installed and power was restored before we left that evening.
Installation timescale
The physical replacement and associated electrical alterations took one full working day.
Because of the additional time required for the cable extensions, trunking and existing conduit arrangements, the final inspection and testing were scheduled for a separate return visit on Monday.
No existing electrical faults have been identified so far, although the final testing is still outstanding.
Inspection, testing and certification
The installation is awaiting its final inspection and testing.
Following satisfactory results, an Electrical Installation Certificate (EIC) will be issued and the consumer unit replacement will be notified under the Building Regulations through NICEIC.